Treasury Ordered to Account for KSh5 Billion Moja Expressway Revenue Shortfall

The National Treasury has been given until Tuesday, November 24, to explain a KSh5 billion revenue deficit reported on the Moja Expressway and provide details of how the shortfall will be addressed.

The directive was issued on Monday, November 23, by the National Assembly’s Departmental Committee on Finance and National Planning, which raised concerns about the accuracy of revenue figures submitted by private concessionaires and the potential financial burden on taxpayers.

During its deliberations, the committee questioned whether adequate mechanisms existed to independently verify revenue reports provided by private operators before the government assumed responsibility for any resulting deficits.

Lawmakers warned that accepting figures submitted by concessionaires without independent audits could expose the government to unnecessary financial liabilities. They also noted that the matter could set a precedent for other major infrastructure projects, including the proposed Rironi-Mau Summit highway.

MPs demand accountability over PPP arrangements

Committee chairperson and Molo MP Kimani Kuria stressed the need for stronger accountability and verification measures in Public-Private Partnership (PPP) agreements.

Kuria maintained that the government should not take responsibility for revenue shortfalls reported by private investors without first establishing their accuracy through independent audits.

He called for clear safeguards to protect public finances and ensure that taxpayers were not left bearing financial obligations without proper scrutiny.

“We must establish clear accountability and verification mechanisms to ensure that revenue shortfalls reported by private concessionaires are independently audited. We cannot allow taxpayers to shoulder financial obligations without proper checks and balances,” he said.

Treasury PS responds to the KSh5 billion deficit

Appearing before the committee, Treasury Principal Secretary Chris Kiptoo acknowledged that addressing the reported KSh5 billion shortfall would require additional funding through a Supplementary Budget.

Kiptoo undertook to submit supporting documents detailing how the revenue figures were verified, the existing financial safeguards and the measures in place to manage the government’s exposure to the deficit.

The committee directed him to provide a comprehensive audit trail by Tuesday, November 24, covering the verification procedures, accountability mechanisms and measures designed to minimise financial risks arising from the shortfall.

Senate previously questioned Roads CS over delayed project

The latest directive comes about a month after Roads and Transport Cabinet Secretary Davis Chirchir was ordered to explain delays, funding arrangements, procurement procedures and the quality of work on the Musikoma-Buyofu-Mungatsi-Myanga-Mateka Road project.

The road project, which has an existing contract value of KSh1.961 billion, has remained incomplete approximately eight years after its original completion deadline.

The Senate’s demand followed a request for a statement by Busia Senator Okiya Omtatah concerning the project’s implementation.

In correspondence to Chirchir, the Office of the Clerk of the Senate cited proceedings from October 7, 2026, when the senator sought clarification from the relevant committee on the delayed works under Road Works Contract 115.

The Senate wanted Chirchir to provide a detailed history of the project, including its procurement and award process, original commencement and completion dates, extensions granted and the reasons for the delays.

Also Read: Treasury Disputes Reports of KSh233.4 Billion Increase in Kenya’s Foreign Debt 

Lawmakers also sought the original tender documents, contract agreements, bills of quantities, award decisions and any subsequent amendments or variations.

Additionally, the committee requested an update on the contract’s current status, including whether it had been terminated, suspended, extended or redesigned.

It also demanded a comprehensive breakdown of public funds allocated, released, committed, certified and paid towards the project since its commencement.

Another issue of concern was the decision to advertise a new tender in 2026, identified as Road Works Contract 1066, for the completion of the second phase of the project despite the existence of the original KSh1.961 billion contract.

The Senate sought the legal, financial and technical justification for awarding the additional contract.